STX substation for Arkona windfarm

On 12 July, STX France’s Saint-Nazaire yard began assembling the substation for the Arkona offshore windfarm being developed by German power utility E.ON, Norwegian group Statoil and German company 50Hertz. The Baltic windfarm, comprising sixty 6-MW Siemens turbines generating enough electricity to power 400,000 homes, is scheduled for completion in 2019.

The 385-MW substation, for delivery in Q2 next year, will be one of the most imposing structures of its type anywhere in the world.

 